Otway Exploration Drilling Program

Otway Exploration Drilling Program

We are exploring the Otway Basin for natural gas to supply the domestic market and support Australia’s current and future energy needs, ensuring reliable power generation, industrial processes, and residential heating.

Project Update as of 1 November 2025

  • Essington-1 drilling has started and is likely to continue through to the end of November
  •  Charlemont-1 drilling is now expected to commence in December 2025
  •  Pre-lay of anchors and mooring chains continues for Charlemont-1. Once in position these will be marked by surface buoys with navigation lights.
  • The Transocean Equinox rig is now operating on behalf of ConocoPhillips Australia while drilling the two wells. Anchors and mooring chains from both locations will be collected within 3 months of the activity completion at each well.